WATER AND SEWER INSTALLATION PROGRESS

I have been in contact with Dwight McMillan at The Park and he has given me an update on the progress of the sewer and water installation. All the main sewer and water lines are in. They are working on services to the individual cabins on the far south of 1st and 2nd Street South. They will be finished all the installation by the end of November. They will come back in the spring to finish cleanup and pressure test lines. This will be done as soon as the frost is out next spring.